Thorn Lighting Post-Tensioned Slab

Date: 12/08/2016

Location: Auckland

Project: Thorn Lighting Post-Tensioned Slab

Another post-tensioned slab on grade design and construct completed by Grouting Services in conjunction with specialist concrete construction company Conset Construction. To deal with the 70kN back to back rack loads and relatively poor subgrade (CBR=3%), a 165mm slab was required. The design, documentation and construction monitoring for the 2,150sq.m slab was completed by EDGE consulting on behalf of Grouting Services.

Contact Us +64 9 837 2510