Project:
Client:
Consultant:
Key Facts:
|
Clifton Road Residences Ground Anchors
Hauraki Piling
Beca
 |
75No. double corrosion protected (permanent) multi-strand anchors (UTS 1,100kN to 3,300kN), 18m to 30m |
 |
3No. full scale sacrificial proving trial anchors (UTS 1,800kN) |
|
|
 |
|
Project:
Client:
Consultant:
Key Facts:
|
Huntly Power Station Grouting
Fulton Hogan
Tonkin & Taylor
 |
1000sq.m ground improvement to 1m thick concrete road |
 |
80cu.m cement-bentonite grouting (15MPa) |
|
|
 |
|
Project:
Client:
Consultant:
Key Facts:
|
Sky City Casino Ground Anchors
Fletcher Construction
Beca
 |
950No. temporary multi-strand anchors (UTS 700kN to 3,500kN), 18 to 25m |
 |
3No. full scale sacrificial proving trial anchors (UTS 2,200kN) |
|
|
 |
|
Project:
Client:
Consultant:
Key Facts:
|
Auckland City Road Grouting
Auckland City Council
City Design
 |
36,000sq.m road stabilisation grouting |
 |
2,000cu.m cement grouting (25MPa) |
|
|
 |
|
Project:
Client:
Consultant:
Key Facts:
|
Dunedin Water Treatment Plant Post-tensioning
Naylor Love
Beca
 |
6No. 66m-diameter 28,000cu.m reservoirs |
 |
36No. 12-strand tendons 74m long per reservoir |
|
| prev 1 2 3 4 5 6 next |